Kenya's oldest geothermal power station, Olkaria I, is set for a major comeback after a Sh15.6 billion upgrade that will boost its generation capacity from 45MW to 63.3MW, strengthening the country's clean energy supply.

Kenya's Geothermal Giant Roars Back: Olkaria I Returns with More Power After Sh15.6 Billion Revival
Olkaria I power plant

Kenya’s clean energy ambitions have received a major boost following the rehabilitation of Olkaria I, the country’s oldest geothermal power station, which is preparing to return to full operation with an upgraded electricity generation capacity after a Sh15.6 billion investment.

The 45-year-old facility, located in Naivasha, Nakuru County, has completed an extensive three-year rehabilitation programme undertaken by the Kenya Electricity Generating Company (KenGen). The upgrade is expected to increase its installed generation capacity from 45 megawatts (MW) to approximately 63.3MW, adding 18.3MW to the national electricity supply.

KenGen Managing Director Peter Njenga confirmed on November 25 that rehabilitation works had been completed, with the facility undergoing reliability tests ahead of its official commissioning, scheduled for December 7, 2026.

The development comes at a critical moment for Kenya’s electricity sector, which is experiencing rising demand and increasing dependence on imported power to supplement domestic generation.

Olkaria I was commissioned in 1981, becoming the first geothermal power station in Africa. Its return marks an important milestone in Kenya’s efforts to strengthen energy security while expanding its renewable electricity capacity.

The rehabilitation involved replacing ageing turbines and generators across the facility’s three generating units, alongside improvements to the steam-gathering system and electrical infrastructure. China’s SEPCOIII and Japan’s Toshiba Energy Systems and Solutions Corporation were involved in the project.

Beyond restoring an ageing facility, the investment demonstrates how modern technology can extract more electricity from existing geothermal resources without requiring an entirely new power station.

Kenya’s electricity demand has continued to climb, with peak demand reaching 2,549MW in 2026, compared with 2,149MW in 2023. Meanwhile, electricity imports from Ethiopia and Uganda increased to 1.91 billion kilowatt-hours in the year ending June 2026, highlighting the pressure on domestic generation.

Geothermal energy remains central to Kenya’s electricity mix, contributing 40.9 per cent of electricity supplied to Kenya Power during the financial year ending June 2026.

Olkaria I’s revival is therefore expected to strengthen reliable baseload electricity supply and reduce pressure on alternative sources.

The project also reinforces Kenya’s position as a geothermal leader in Africa, demonstrating that investment in existing infrastructure can unlock additional generation capacity.

After more than four decades of service, Olkaria I is preparing for a new chapter, bringing renewed power to Kenya’s national grid.